Saller lifts Bavarian bridge

1 September 2020

Print Page

Deggendorf, Germany-based Kran Saller, used two Liebherr all terrain cranes to carry out a tandem lift of a 60t component of a pedestrian bridge over a railway track. The cranes were position very close to each other for the overnight job in Munich and were within 20cm of touching during the lift.

“Normally we would have hoisted the load with just one crane and an adjustable yoke, but the customer insisted that the work should be carried out using two cranes”, said Klaus Ruhland, who completed the calculations for the tandem hoist together with Dennis Kase.

It was tight with only 20cm between the telescopic boom of the LTM 1750-9.1 and the ropes on the telescope guying of the LTM 1400/1 when the cranes’ superstructures reached the trickiest moment of the complex slewing process.

The LTM 1750-9.1 had to reach over the smaller crane and its boom to pick up the load, so the massive nine-axle machine was set up with a 35m luffing jib and its telescopic boom was extended to almost 40m for the actual hoist.

“The close positioning of the two cranes was due to the fact that we had to work from the abutment of a road bridge. We were not able to position the cranes on the bridge structure as a result of the support pressures they generate.” said Franz Saller, managing director and head project manager.

Full closure of the rail network and the road for the hoisting and set-up work was required. But the job was carried out quickly and smoothly during the night in the Bavarian capital by the team from Kran Saller.

The actual hoisting of the bridge component took exactly one hour, after which it was positioned around 30m away on the piers of the future bridge. Immediately after the load had been detached, the team started dismantling their Liebherr cranes.

The reinforced concrete component was placed on its piers at a distance of 30m over the closed rail track.
Kran-Saller used lots of equipment and manpower to hoist a component for a pedestrian bridge weighing 61t into place in Munich-Solln.
Tested beforehand by computer simulations, the telescopic booms and ropes for the Y guying came very close to each other during the slewing process.
Two cranes, including an LTM 1250-5.1, place the load on a low loader.
The 750t mobile crane picked up the load from a distance of 37m and had to reach over the LTM 1400/1.