A 510t lift for Tiong Woon

29 January 2020

Print Page

Tiong Woon has deployed its Demag CC 8800-1, assisted by a CC 2800-1, to lift a 510t vessel in Singapore. Unusually for such a big crane, Demag’s Boom Booster was needed for the job.

The crane was first set up offsite, for a test lift in line with local regulations. Once the test was complete, it was disassembled and transported to the Merlimau Road jobsite and reassembled.

Setting up the crane with its seven-part Boom Booster kit took the team, which consisted of six assembly technicians, six signal persons, and two supervisors, a total of five days – that is only one day more than the standard configuration would have taken. “In order to speed up the process, one part of the team took care of assembling the base crane, while the other part took care of setting up the Boom Booster,” said Tiong Woon’s deputy chief executive officer Michael Ang.

For the CC 8800-1 primary crane with the Boom Booster kit, Tiong Woon chose a BSFVL configuration with a main boom length of 102m plus a fly jib of 12m mounted at an angle of 14°. Meanwhile, the required Superlift counterweight came in at 400t. For the Demag CC 2800-1 assist crane, the company chose an SSL configuration with a main boom length of 42m and a Superlift counterweight of 100t.

Once set up this way, the Demag duo was ready to lift the 100m-long, 510t steel pipe with a diameter of 4.84m. The biggest challenge was to bring the massive steel structure from a horizontal position to a vertical position on the Demag CC 8800-1’s hook in a controlled manner by using a tailing operation.

To do this, the CC 2800-1 first picked up the splitter column from its end in order to then lift it to a height of 0.5m. At the same time, the CC 8800-1 lifted the load from its other end while the CC 2800-1 slowly moved forward until the splitter column was hanging from the CC 8800-1’s hook and the assist crane was no longer under load. After the team released the CC 2800-1’s slinging gear, the CC 8800-1 brought the splitter column to the required position in order to set it down exactly at the intended point.

“Tandem lifts are already complex operations in and of themselves, but when you add a heavy load with this type of dimensions, things get even trickier,” Ang said. Accordingly, the job was meticulously planned. A technician and a mechanic were there at the work site, ready to fix any issues that might have occurred.

This conscientious preparation was an important reason why the Tiong Woon team was successful in carrying out the project to the customer’s full satisfaction, and a few days earlier than scheduled. “We were at the work site for a total of 69 days with our cranes and 25 people on average. The fact that the weather conditions were ideal and, especially, that the two Demag cranes have such incredible performance characteristics played a crucial role in enabling us to finish the project earlier than planned: this goes particularly for the CC 8800-1 with the Boom Booster, which was an absolute requirement in order to be able to lift a load with these dimensions and this weight,” Ang said.

“We were also tremendously thankful for the support provided by the Demag team during the test setup. It served as further confirmation of the fact that we can always rely on Demag for fast and expert help with any issues at any time, which is why we’ve always been happy with the service they provide.”