Leading the project was Robert LaChapelle, Able’s partner / VP and Master Rigger. "Pre-planning the logistics and engineering started in early 2014", said LaChapelle.

"We used a 70,000lb capacity Timberland ASD 35/120 Stiffleg Derrick, and chose a GP500 hoist pack with 50,000lb single part line pull (with a 32mm python no spin cable), to be the primary hoisting package for the derrick."

Because of very tight working conditions, a unique runway ramp was constructed on the roof to aid in the storage of the derrick’s boom when it was not in service. The 100lb per sq ft capacity ramp was positioned at a 15ft cantilever off the building.

Once the derrick was constructed the Able team load-tested it prior to the MR415 recovery. The Potain’s boom was removed and disassembled into 4 pieces, and then strategically lowered in a vertical position to 56th Street to allow for enough building clearance. The upper works were then removed and lowered. The crane’s 14 tower sections were next. They were lifted out of the interior climbing collars and dunnage of the building in pairs, and then lowered to street level.

Almost all lifts were accomplished at a 70ft radius, allowing a 25ft clearance to the front of the building. For pieces with larger surface areas, Able used two 1,500ft taglines.

"The bottom of the MR415 started at the 75th floor at a 1,285ft elevation and the top was at an elevation of more than 1,500ft, at the 85th floor," said LaChapelle. "The GP 500 hoist permitted six to eight lifts to the street, traveling at 85 feet per minute in high speed, which gave us a 14,000lb line pull, and nearly 50 feet per minute in low speed, with a 50,000lb pull."

When empty lifts occurred, the team utilised 4,000lbs of overhaul weight together with a ball weighing 35US tons.

With the Potain now recovered, the Able team dismantled the derrick and transported it down via the building’s hoist elevator.

"Lifts to the street were made in winds up to 15mph, with the derrick operating on the roof in winds up to 30mph," said LaChapelle. "We lost approximately five days due to high wind or rain with clouds and fog being a challenge."

Building the derrick took three days. It took two days to calibrate and load test its computer, and five days to recover the Potain MR415. A Tier 4 Cummins diesel engine was utilised for all hoist power modules. Controls and communication systems were installed in a repurposed tower crane cab customized by Able Rigging.

Able Rigging’s client was Roger & Sons Concrete, Howard I. Shapiro Engineering Associates was the engineer of record, and the construction manager was Lend Lease Corp.