The projects, completed over the last five months, included the transportation and installation of a 605t CO2 absorber column in Darwin.

At Cape Lambert in Western Australia, ALE installed two 400t car dumper cells using the LR11350.

ALE’s projects and technical director Filippo Anello said of the project in Darwin: "With limited space for the positioning and manoeuvring of the crane on a live gas plant, the lift and transport planning were carefully engineered to complete the operation safely."