Hareket used four Goldhofer SPMTs including a 20-axle PST/SL-E, a 16-axle THP/SL and a 24-axle THP/SL.

The vessels, which were shipped from Japan, arrived in the Port of Derince where they were unloaded using the SPMTs and stored at the port for a brief period. They were then reloaded to the SPMTs and moved onto a barge, which was then towed to the port of Tüpras. On arrival the SPMTs were driven from the barge to shore and moved to an assembly area. Once in place, the reactors and coke drums were erected by a 1350t Liebherr LR 11350 and a 600t Demag CC 2800-1.